M3M Mansion RERA Possession Date & Construction Update

military_techPublisher: M3M Properties
eventLast Update: Nov - 06, 2026
personAuthor: Sumit Mishra

M3M Mansion is a high-rise residential project in Sector 113, Gurugram, on the Dwarka Expressway. It is built in two phases, and each phase has its own RERA registration and completion date. That is why buyers find different possession dates online.

This page explains the construction status, the RERA completion dates for both phases, and how construction progress leads to possession. It also shows how to read the Haryana RERA quarterly report, so buyers can check progress for their own tower.

M3M Mansion – Latest Project Update

M3M Mansion is under construction. The RERA completion date is 29 February 2032 for Phase 1 and 28 February 2031 for Phase 2. No occupancy certificate or possession offer has been reported.

ProjectM3M Mansion, Village Chauma, Sector 113, Gurugram
Developer brandM3M India
Registered promoterUnion Buildmart Pvt. Ltd.
Project typeMixed land use colony with residential apartments
Phase 1 RERAGGM/802/534/2024/29, dated 18 March 2024
Phase 2 RERAGGM/916/648/2025/19, dated 20 February 2025
StatusUnder construction

Phase 2 was registered as “M3M Mansion Ph-2”. HARERA records now show it under the name M3M St. Andrews at SCDA. Buyers who booked in either name should check the RERA number on their allotment letter.

M3M-Mansion-possession-date

M3M Mansion Phase 1 vs Phase 2 – Construction and Possession Status

DetailPhase 1Phase 2
RERA numberGGM/802/534/2024/29GGM/916/648/2025/19
Registration date18 March 202420 February 2025
Layout and building plan approval20 February 202427 January 2025
Construction start1 March 2024Stated in the RERA project record
RERA completion date29 February 203228 February 2031
Scale8 towers, up to ground plus 32 floorsSmaller site of about 1.2 acres, as reported in project listings
Developer’s timelineFrom December 2029, phase-wise, till 2032Completion listed as Q1 2031
Progress reportingSeparate quarterly reportSeparate quarterly report

M3M Mansion Construction Update

Construction began on 1 March 2024, as filed with RERA, and continues across the site. The project is not ready to move in.

Current Construction Progress

Phase 1 has eight towers planned to a height of ground plus 32 floors. Towers of this height are built in a fixed order: excavation and foundation, basement, tower structure, brickwork, services, façade and finishing. Public project pages do not publish a tower-by-tower stage list for M3M Mansion. The stage reached by each tower appears in the promoter’s quarterly progress report on the RERA portal.

Latest Construction Report and Site Updates

Every registered promoter files quarterly progress reports. These show the percentage of work done and the declared completion date. Buyers should read the latest report for their own phase. Phase 1 and Phase 2 report separately, so one report does not describe the other.

A dated site visit to your own tower gives a useful second check. Photos should carry a date and the tower name.

What Construction Work Is Still Pending?

The RERA dates show that most of the work is still ahead. Phase 1 has about five years to its filed completion date, and Phase 2 has about four. The pending work includes the remaining tower structure, internal work, services, façade, finishing and external development. The latest quarterly report lists what remains for each tower.

M3M Mansion Possession Date – Official vs Expected Timeline

TimelineWhat it isStatus
29 Feb 2032Phase 1 RERA completion dateOfficial, as filed
28 Feb 2031Phase 2 RERA completion dateOfficial, as filed
From Dec 2029, phase-wise till 2032Statement on M3M’s project pageDeveloper’s marketing timeline
Date in your agreementContractual possession dateBinding on you. Check your document
Broker dates such as Dec 2027 or March 2030Estimates on listing sitesNot official

M3M Mansion RERA Completion Date

For Phase 1, the filing shows completion on 29 February 2032. The same filing shows registration valid until 31 March 2030, which is earlier than the completion date. Buyers should read the registration certificate and ask the developer in writing how the two dates relate and whether any extension applies. For Phase 2, the record shows completion on 28 February 2031.

Is the RERA Completion Date the Same as the Possession Date?

No. The RERA date is the deadline declared to the regulator. The possession date is written in the builder-buyer agreement and may include a grace period. Possession also needs an occupancy certificate and an offer letter, so handover usually comes after construction ends.

Has M3M Mansion Possession Been Delayed?

No delay has been recorded. Both RERA completion dates are still ahead, and no extension has been filed for either phase. A delay is measured by comparing the agreement date with the actual handover.

How Does M3M Mansion Construction Progress Affect Its Possession Date?

Possession can happen only after structure, services, finishing and statutory approvals are complete. Each stage depends on the one before it.

  • Structure: Foundation, basement and tower floors are built first. Later work cannot start on a floor until it is in place.
  • Internal work: Brickwork, plaster, flooring and doors follow once the structure is ready.
  • MEP work: MEP means mechanical, electrical and plumbing. It covers wiring, water lines, drainage, lifts and fire safety. Lifts and fire systems must be tested before a tower can be approved.
  • Façade and finishing: The outer cladding, painting and fixtures are completed.
  • Occupancy certificate: The promoter applies after the tower is complete. The certificate confirms the building is fit to be occupied.
  • Possession offer: The developer writes to each buyer. The offer asks for final dues and sets a handover date.
  • Handover: The buyer inspects the apartment and receives the keys.

M3M Mansion Construction Timeline – Important Milestones

DateMilestone
20 Feb 2024Layout and building plans approved (Phase 1)
1 Mar 2024Construction start, as filed (Phase 1)
18 Mar 2024Phase 1 registered with Haryana RERA
24 Jan 2025Phase 2 application submitted
20 Feb 2025Phase 2 registered (GGM/916/648/2025/19)
28 Feb 2031Phase 2 RERA completion date
29 Feb 2032Phase 1 RERA completion date

How to Read the M3M Mansion Haryana RERA Quarterly Progress Report

Search the RERA number on haryanarera.gov.in, open the project page and find the progress report. These are the parts that matter:

  • Physical progress: The percentage of work done, split by component such as structure, finishing and services. Compare tower by tower.
  • Financial progress: Money received from buyers against money spent on the project. Spending that lags collections is worth a question to the developer.
  • Declared completion date: The date the promoter commits to the regulator. Check that it matches the date in your agreement.
  • Extension details: Any approved extension must be shown. A date that moves between reports is a signal to ask why.
  • Report date: An old report says little about today. Look for the latest quarter.
  • Phase: Make sure the report belongs to your phase and RERA number.

The strongest check is to compare two consecutive quarters. Steady increases in physical progress and an unchanged completion date are a good sign. Flat percentages across two quarters should prompt a written question to the developer.

Project Completion vs Possession – What Is the Difference?

TermMeaning
Construction completionThe building work is finished
Occupancy certificateThe authority confirms the building is fit to occupy
Possession offerThe developer invites you to take the apartment after dues are cleared
Actual handoverYou inspect the apartment and receive the keys

What Should Buyers Know About Possession Delays?

Rights depend on the signed agreement and the RERA Act, 2016. Under Section 18, if a promoter misses the agreed date, a buyer can generally choose to withdraw and receive a refund with interest, or stay and receive interest for each month of delay. Section 6 allows extensions in cases such as force majeure.

Keep these documents ready:

  • The builder-buyer agreement and its grace period clause.
  • Payment receipts and demand letters.
  • Written communication from the developer.

Complaints go to Haryana RERA, Gurugram. This is general information and not legal advice. Outcomes depend on each agreement.

What Should Buyers Verify Before Taking Possession?

CheckWhy it matters
Possession offer letterIt states the legal handover date
Occupancy certificateIt confirms the building is approved for use
Completion certificate, if applicableIt confirms the work matches approved plans
Final payment statementIt avoids disputes about dues
Maintenance chargesThey set your running cost
Apartment inspection and defect listThey give you a written record for repairs
Utility connectionsWater, power and sewer should be active
Handover documentsKeys, manuals, warranties and agreements